Project Name

30-36 Mildred Avenue

Project Parcels

1800808000

30 MILDRED AV
Owner:
City of Boston - DND
3,542sqft

1800805000

36 MILDRED AV
Owner:
City of Boston - DND
3,526sqft

1800806000

34 MILDRED AV
Owner:
City of Boston - DND
3,523sqft

1800807000

32 MILDRED AV
Owner:
City of Boston - DND
3,542sqft
Project Images
Neighborhood
Mattapan
Councilor
Arroyo
Units Total
Six
Income-Restricted Units
Six
Property Size
14,133 sq/ft

Developer

Norfolk Design & Construction LLC

Minority Owned Business
Veteran Owned Business

Project Goals

30-36 Mildred Ave will be developed by Norfolk Design & Construction in partnership with The Trustees of Reservations. When complete, the project will consist of one building with six affordable, for-sale homeownership units, and a community garden of approximately 7,000 square feet.

Timeline

Winter 2019

Community Feedback

We’re meeting with community members to gather feedback on plans for the site.

Dec 06 2019
Join us for a community discussion on the potential development of these parcels. The Department of Neighborhood Development is looking for neighborhood input on how these parcels could best be put to use. DATE: Monday, January 6th, 2020 TIME: 6:30 - 8:00 LOCATION: Mildred Ave Community Center, 5 Mildred Ave, Mattapan
Campbell Stras | Project Manager
Aug 14 2020
The Department of Neighborhood Development (DND) and the Greater Mattapan Neighborhood Council invite you to a Virtual Community Meeting to discuss the upcoming property disposition process for four (4) City-Owned parcels of vacant land located at 30-36 Mildred Avenue, Mattapan (Ward 18, Assessors Parcel Numbers: 00808, 00807, 00806 and 00805). This meeting will be held through video conferencing. We encourage you to attend this meeting and provide feedback for the development guidelines to be used in the upcoming Request For Proposals (RFP). DATE: TUESDAY SEPTEMBER 8th, 2020 TIME: 6:30 P.M. 8:00 P.M. Please register for the ZOOM Meeting in advance, using your name and email, by visiting: https://zoom.us/meeting/register/tJwpcuCoqj4oEtxJl3-NbQaZvMRkEIzt8QJ_ Please do not share the Zoom meeting link you receive after you register.
Campbell Stras | Project Manager
Sep 09 2020
Thank you to everyone that attended the meeting. Please leave any ideas, suggestions, thoughts or comments on what you would like to see here at 30-36 Mildred Avenue. The comment period will be available until Wednesday, September 23, 2020. I look forward to hearing from you
Campbell Stras | Project Manager
Spring 2022

Developer Selection

We’ll release a Request for Proposals and select a developer for this site.

May 2, 2022

Request for Proposals (RFP) Opened for Bidding

Jun 01 2022
30-36 Mildred Ave RFP Applicant Conference
Jun 01 2022 3:00-4:00PM

Jan 05 2023
30-36 Mildred Ave Developer Presentation
9 ATTENDEES

Thank you to everyone who attended the presentation of the 30-36 Mildred Ave affordable housing and community garden development proposal by Norfolk Design & Construction and The Trustees! There will be a public comment period in response to this presentation from January 5 until January 15, 2023. Comments can be submitted using the Google Form at bit.ly/30-36mildredcomment or through email to stephanie.silva2@boston.gov

Winter 2023

City Planning

This project is going through a zoning review with the Boston Planning and Development Agency (BPDA). Then we’ll work with the Developer on funding, design, and compliance.

Under Construction

Predicted Date: Summer 2024

Project Complete

Predicted Date: Fall 2025